Close

    ADDC Leh reviews Telecom Connectivity in Vibrant Villages.

    Publish Date: November 29, 2024
    WhatsApp Image 2024-11-28 at 22.03.14

    Leh, November 28, 2024: The Additional District Development Commissioner Sonam Nurboo convened a meeting to review the progress of telecom connectivity in Vibrant Villages of Ladakh at the VC Room, DC Office, Leh.
    During the meeting, BSNL officials presented a progress report on tower foundation completion, tower erection completion, electrical works completion, TCS I&C completion, and tower radiating (on air).
    The officials informed that tower foundations in 27 villages have been completed, while tower erection has been completed in 20 villages. Power infrastructure installation has also been completed at 10 sites. The officials stated that work is ongoing and is expected to be completed by next year.
    Telecom connectivity issues at Chumur and Thang villages were also discussed during the meeting. ADDC Leh thoroughly reviewed the progress and instructed the officials to expedite their work.
    The meeting was attended by officials from BSNL, Jio telecom and PDD Department.